Construction of Cement’s Plant Production

Client: Anarak Cement Company
Location: Delijan
Duration: 2005-2008
The scope of work is the civil and infrastructural works of Delijan grey cement plant's production line, including limestone crushing plant, raw mill feed bunkers, raw mills, coolers, ESP (electrostatic
precipitator), de-dusting units, cement silos, clinker silos, packing and loading plant, blending silo and administration building. The quantities of major items such as earthworks, concrete and structural works as follow:
 Earthwork: 160,000 cubic meters  Concrete: 95,000 cubic meters  Reinforcement: 12,000 tonnes  Formwork: 160,000 square meters  Heavy steelwork: 4000 tonnes

The Khanesazi Building

Client: Khanesazi
Location: Gulf
Contract No.:1/1/1474
Duration: 2005-2007
This project provides a building complex for the social department which comprises of one block in two floor for administration building (3’000m2), three blocks in two floors for residential buildings (4’000m2) with all relevant landscaping works (10’000m2) and MEP works.

Land Drainage at The South Cluster

Client: TOTAL
Location: DOROOD Oilfield
Contract No.: EPI-0368
Duration: 2005-2006
This project comprises of EPIC for the drainage of low laying land and adjacent to the south cluster, in order to provide flood prevention measures to the concrete platform, manifold area and other hard standing of said cluster.

The Oil Loading Terminal

Client: TAISEI
Location: Gulf Onshore
Contract No.:TTB/C/003
Duration: 2004-2005
The project includes rehabilitation and construction of south part of T-Jetti Terminal which comprises of offshore piling, pitching of jacking, demolition and construction of new steel structure.